National Grid’s contractor, NEUCO, will be mobilizing to #SalemMA to replace the gas main on Harbor Street (including the intersections where Salem Street and Park Street meet Harbor Street) starting the week of January 2, 2023.
1
219
The scope of work includes the installation of new plastic gas main & installation of new plastic services for residents and businesses of the area. The area that will be directly affected by the gas main replacement is: 5 to 73 Harbor St (including 1-6 Salem St & 1-6 Park St)
1
139
Length of main: approximately 1,500 feet Start date: week of January 2nd Duration: approximately 7 weeks, weather permitting Work hours will be 7:00AM to 3:30PM weekdays, no work weekends or holidays. Police details will be present at all times to facilitate traffic management.
117
NGrid Beverly cable project work in #SalemMA week of January 2, 2023: •Continued activity on National Grid property on the corner of Ferry St & Waite St as crews work on Waite St substation. •Duct bank excavation & conduit installation on Bridge St, between Pierce Ave & bridge.
1
183
Please note that parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street to allow for greater access for National Grid and its contractors. Construction will take place between the hours of 7:00 am and 4:30 pm, Tuesday through Friday.
117
Work in #SalemMA for National Grid Beverly cable replacement project: •Activity on National Grid property on the corner of Ferry St and Waite St as crews work on Waite St substation. •Duct bank excavation and conduit installation on Bridge St, between Pierce Ave and bridge.
1
183
Please note that parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street to allow for greater access for National Grid and its contractors. Construction will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday.
1
97
At this time, no project activities are expected during the week of December 26. Crews are expected to commence project activities on Tuesday, January 3, following the observance New Year’s Day.
59
This week in #SalemMA from National Grid Beverly cable replacement project: •Activity on National Grid property on corner of Ferry St & Waite St as crews work on the Waite St substation. •Duct bank excavation & conduit installation on Bridge St, from Pierce Ave to the bridge.
1
Please note that parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street to allow for greater access for National Grid and its contractors. Construction will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday.
Work in #SalemMA this week for the National Grid Beverly cable replacement project: •Activity on National Grid property on the corner of Ferry St & Waite St for the Waite St substation. •Duct bank excavation & conduit installation on Bridge St, between Pierce Ave & bridge.
1
Please note that parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street in Salem to allow for greater access for National Grid and its contractors. Construction will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday.
Starting the week of November 28, National Grid’s contractor (McCourt Construction) is expected to begin excavation for manhole installation on Bridge Street, between Ames Street and the Essex Bridge. Work will take place between 7:00 am and 4:30pm, Monday through Friday.
1
Work this week in #SalemMA for the National Grid Beverly cable replacement project: •Continued activity on National Grid property on the corner of Ferry Street and Waite Street as crews work on the Waite Street substation.
1
•Duct bank excavation and conduit installation on Bridge Street, between Pierce Avenue and Essex Bridge. Parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street in Salem to allow for greater access for National Grid and its contractors.
1
Construction will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday. Crews will not work on Thursday of next week due to the holiday but will return to work on Friday.
Work this week in #SalemMA for the National Grid Beverly cable project: •Work on National Grid property at corner of Ferry St & Waite St as crews work on the substation. •Duct bank excavation/conduit installation on Bridge St, from Pierce Ave to the bridge.
This week you can expect the following activities in #SalemMA for the National Grid cable project: •Continued activity on National Grid property at Ferry St & Waite St as crews work on the Waite St substation. •Duct bank excavation on Bridge St, between Peirce Ave & bridge.
Starting the week of Nov 1, National Grid’s contractor (McCourt Construction) is expected to begin duct bank excavation on Bridge Street in #SalemMA, between Peirce Avenue and the Essex Bridge. Work will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday.
1
As a result of this work, parking on Bridge St may be limited during working hours. Expect to see an excavator on the road, as well as a vacuum truck used for the removal of soil when machine excavation is not possible. More info: beverlyregionaltransmissionr….