TXDOT Hwy 35 Project Update
Scope
• PAVEMENT REPAIR, SEAL COAT, AND 1.5-INCH ACP OVERLAY
Timeline
• 1.5 INCH ACP OVERLAY – ESTIMATED COMPLETION SEPTEMBER 5TH
• FINAL STRIPE – ESTIMATED COMPLETION SEPTEMBER 30TH
• REMOVE & REPLACE SIGNS – ESTIMATED COMPLETION OCTOBER 3RD