Building a stronger water future for San Diego 💧 On the Morena South and Middle project, crews have installed over 52,000 linear feet (nearly 10 miles!) of pipeline. Once complete, pipelines will convey wastewater and brine for recycling and purification. #Path2PureWater
3
2
3
1,361
Recently, construction crews assembled and via crane, lifted a 150’ diameter dome to cover 1 of the 4 secondary clarifiers at the North City Reclamation Plant. Secondary clarifiers help separate biosolids from clean, treated water to increase water quality! #Path2PureWater
3
5
1,537
#Path2PureWater: Progress continues on the dechlorination facility on Meanley Drive! Walls have been installed, and site utility connections are being made. 💡💧This facility will remove the chlorine used to disinfect the purified water before it's stored in Miramar Reservoir.
4
86
On the Morena Northern Pipeline and Tunnels project, contractors used the boring machine shown here to tunnel under Genesee Ave near Rose Canyon. Once complete, this pipeline will help deliver water to the North City Pure Water Facility for purification. 💧 #Path2PureWater
1
2
99
#Path2PureWater: The North City Pure Water Facility is the cornerstone of Phase 1! 💧 With over 70% of construction complete, we are close to producing 32 million gallons of purified water a day for our City. 📸 Our operations and maintenance building nearing completion.
1
2
614
🚧 #Path2PureWater: Today, construction along Nobel Drive has moved west for the Morena Northern Pipeline & Tunnels project. Crews are installing pipeline between Via Las Rambles and Lombard Place during the day, and the work will continue through Summer 2024.
1
2
295
The @CityofSanDiego has one of the largest and most complex water storage, treatment, and delivery systems in the world. Once complete, projects within the Pure Water San Diego program will be an integral piece to the City’s water infrastructure! 💧🏗️ #Path2PureWater
1
2
702
🌊💙 Dive into World Oceans Day with Pure Water San Diego! In addition to serving as a local water source for the region, Pure Water San Diego will reduce treated discharges into the Pacific Ocean by over 50 percent! 🐠💧 #WorldOceansDay #Path2PureWater
2
97
Progress continues at the North City Pure Water Facility! This photo shows a brand-new UV reactor vessel that was just installed. ⚡ The facility will have three of these awesome vessels to finish off the Pure Water treatment process. #Path2PureWater
4
160
It’s Valentine’s week! 💙 We love the progress at the @CityOfSanDiego Morena Pump Station project, which will divert wastewater from Morena area to the North City Water Reclamation Plant for treatment to recycled water standards. #Path2PureWater
2
109
#Path2PureWater: Crews are making progress at the @CityofSanDiego Pure Water Morena Pump Station project. Crews are continuing to form the reinforced walls that will make up the foundation of the pump station
2
7
655
#Path2PureWater: Crews have assembled the “spine” of the @CityofSanDiego Pure Water subaqueous pipeline, or underwater pipeline, at Miramar Reservoir. The pipeline will be sunk before the “arms/legs” are connected under water. Read the news release🗞️: sandiego.gov/sites/default/f…
4
153
#Path2PureWater: 🚧 Crews are making progress at the @CityofSanDiego Pure Water Morena Northern Pipelines & Tunnels project. More than 1,236 linear feet of pipeline has been recently installed along Genesee Avenue and on Towne Centre Drive. Learn more: sandiego.gov/public-utilitie…
1
3
147
#Path2PureWater: There's a buzz of energy at North City Pure Water Facility ⚡️ Construction crews are installing the roof and the reverse osmosis equipment, which brings the facility to more than 55% completion.
1
2
181
Pure Water Phase 1 is more than 40% complete!⚡️A drought-resilient and local #watersupply is on the way for #SanDiego. Visit Phase1.PureWaterSD.org to learn more. #Path2PureWater 🥤
6
161
#Path2PureWater: We’re making waves for the next phase of the Pure Water SD Subaqueous Pipeline project at Miramar Reservoir!💧This pipeline is one-mile long and will rest on the lakebed. The underwater pipeline work is now underway. #potablereuse sandiego.gov/sites/default/f…
2
109
#Path2PureWater: Construction continues on Towne Centre Drive near Towne Centre Gateway for the @CityofSanDiego Pure Water Morena Northern project. Crews are installing one 48" pipe and one 30" pipe in a 20-ft trench.
1
2
165
#Path2PureWater: For the @CityofSanDiego Morena Conveyance South/Middle project in Clairemont/Bay Ho, crews are installing pipeline on Clairemont Dr. to extend up to Rappahannock Ave. during the day and welding the pipeline at night. 🚧 Learn more: sandiego.gov/sites/default/f…
1
2
244
#Path2PureWater 🚧: Construction crews are making progress on Genesee Ave for the @CityofSanDiego Morena Northern Pipelines & Tunnels project. The last sticks of pipeline are being installed on Genesee near Governor. Crews are also preparing for nighttime intersection work.
1
2
305
#Path2PureWater: Construction crews completed paving and curb and gutter work on Executive Dr. between Judicial Drive & Towne Centre Dr. for the @CityofSanDiego Morena Northern Pipelines & Tunnels project. Currently, crews are working just south of La Jolla Village Drive. 🚧
2
4
405