Current Bill of Quantities Estimate for a Standard 3-Bedroom Bungalow
For a standard 3-bedroom bungalow of approximately 140m² to 180m² floor area, the following quantities and costs are realistic market estimates. Actual figures will vary depending on location, design, etc
Land cost is excluded from this estimate.
Professional Services
Architectural drawings
Structural drawings
Electrical drawings
Mechanical drawings
Bill of Quantities
Site supervision
Estimated cost:
₦800,000 – ₦2,500,000
Foundation Stage
Excavation
Hardcore filling
Laterite filling
Compaction
Foundation blockwork
DPC
Oversite concrete
Reinforcement
Concrete works
Estimated quantity:
Cement: 80 – 120 bags
Sharp sand: 2 – 4 trips
Granite: 2 – 4 trips
Reinforcement: 1.0 – 2.5 tonnes (depending on the structural drawings if it’s a swampy area)
Estimated cost:
₦4,000,000 – ₦8,000,000
Walling Stage
9-inch blocks: 1,500 – 2,000 pieces (external walls)
6-inch blocks: 800 – 1,200 pieces (inner walls)
Cement for laying: 70 – 120 bags
Sharp sand: 3 – 5 trips
Lintel concrete
Columns
Labour
Estimated cost:
₦4,500,000 – ₦8,500,000
Concrete Frame
Columns
Beams
Lintels
Structural members
Estimated quantity:
Cement: 40 – 80 bags
Granite: 1 – 3 trips
Sharp sand: 1 – 2 trips
Reinforcement: 1.5 – 4 tonnes
Estimated cost:
₦2,500,000 – ₦7,000,000
Roofing Stage
Steel roof trusses
Long-span aluminium roofing sheets
Ridge caps
Fascia boards
Gutters
Labour
Estimated cost:
₦5,000,000 – ₦12,000,000
Depending on roof complexity and sheet gauge.
Plastering and Screeding
Internal plastering
External plastering
Floor screeding
Estimated quantity:
Cement: 80 – 150 bags
Sharp sand: 4 – 8 trips
Estimated cost:
₦3,000,000 – ₦6,500,000
Electrical Installation
Conduits
Cables
Sockets
Switches
Distribution board
Light points
Labour
Estimated cost:
₦1,500,000 – ₦4,000,000
Mechanical Installation
Water supply pipes
Drainage pipes
Water closets
Wash hand basins
Kitchen sink
Inspection chambers
Septic system connections
Estimated cost:
₦1,500,000 – ₦4,500,000
Doors and Windows
Security doors
Internal doors
Aluminium windows
Burglar proofs
Installation
Estimated cost:
₦3,000,000 – ₦8,000,000
Ceiling Works
POP ceiling or PVC ceiling
Suspension members
Finishing
Labour
Estimated cost:
₦1,500,000 – ₦5,000,000
Floor and Wall Finishes
Floor tiles
Wall tiles
Tile adhesive
Grouting
Labour
Estimated cost:
₦2,500,000 – ₦8,000,000
Painting
Wall preparation
Primer
Emulsion paint
Texcote
Labour
Estimated cost:
₦1,000,000 – ₦3,500,000
External Works
Soakaway
Septic tank
Drainage
Interlocking
Concrete apron
Gate installation
Estimated cost:
₦2,000,000 – ₦10,000,000
Realistic Total Project Cost
Basic finish:
₦35,000,000 – ₦50,000,000
Standard finish:
₦50,000,000 – ₦75,000,000
Premium finish:
₦75,000,000 – ₦120,000,000
Important Disclaimer
This is not a final Bill of Quantities.
A proper BOQ can only be prepared after obtaining:
Architectural drawings
Structural drawings
Electrical drawings
Mechanical drawings
Site information
Soil investigation report where necessary
The quantities and rates above are preliminary market estimates based on current construction trends in Nigeria and should not be used as contract documents
Professional Advice
Before you start building, spend money on planning
Many people know the current price of cement but do not know the total cost of their project
That is why some projects stop at foundation level, lintel level, or roofing level
A proper Bill of Quantities tells you:
How much the project will likely cost
The quantity of materials required
The cash flow needed at each stage
Where savings can be achieved without compromising quality
Remember this:
The most expensive part of a building project is correcting mistakes that proper planning would have prevented