*MP Kirti Azad asked question about Amrit Bharat Station Scheme in West Bengal.*
To this Hon’ble Railway Minister Ashwini Vaishnaw Ji answered,
that the *current budget allocation for West Bengal has increased to 14,205 Cr. compared to 4,300 Cr. during the 2009-2014 UPA period.*
He stated that projects are delayed because only 57% of the required 4,662 hectares of land has been acquired, citing specific projects with zero land acquisition, and requested the MP to ask the Chief Minister to facilitate these railway projects.