@heronpower we are publishing our vision for how future native 800 VDC data centers will be built.
There's plenty of discussion circulating on 800V data centers, and our work stands apart in two key ways. First, it's an end-to-end blueprint for an AI factory data hall, fully specifying a 12 MW building block with bill of materials, redundancy topology, floor layout, and product specs benchmarked against ERCOT's large load interconnection requirements. Second, it line-item the costs and labor breakdowns per MW for our blueprint compared to traditional 480 VAC builds.
Stacked against today’s tech, Heron’s architecture is 1/3 the MV-to-rack electrical cost, 1/10th the installation labor, and half the inefficiency from grid to chip, unlocking faster, more affordable, gigascale buildouts.
Read the full details here:
heronpower.com/blueprint-for…